SIZEWELL B PUBLIC INQUIRY: VOLUME THREE PART II SECTIONS 6-10:
01 January 1991
SIZEWELL B PUBLIC INQUIRY: VOLUME THREE PART II SECTIONS 6-10:
REPORT ON APPLICATIONS BY THE CENTRAL ELECTRICITY GENERATING
BOARD FOR CONSENT FOR THE CONSTRUCTION OF A PRESSURISED WATER
REACTOR AND A DIRECTION THAT PLANNING PERMISSION BE DEEMED TO BE
GRANTED FOR THAT DEVELOPMENT INQUIRY 11 JANUARY 1983 - 7 MARCH
1985
refdoc August=1991
BOOKS/PAMPHLETS , User Ref = 621.039.577 , Acc Date = 01-Apr-87
F Layfield , Department of Energy
HMSO, 1987 Various pagings, tables RB45052
Looks at radiological risks from the plant, criticism of safety
criteria, safety aspects of the nuclear fuel cycle and other
safety issues. Considers alternative opinions on the risks from
radiation, radiation doses to workers, radiation doses to the
public from normal operation, the consequences of accidents and
incidence of leukaemia near Sizewell. Safety aspects on spent
fuel transport, radiological consequences of reprocessing and
solid radioactive waste management are examined as well as
safety issues on emergency plans, decommissioning, war and
sabotage, the Three Mile Island accident, nuclear safety and
public confidence.
United Kingdom, nuclear power, nuclear energy, pollution, Wales,
electricity generation, shielding, nuclear waste, evacuation,
cancer, London, England, Flowers Report, Harvey Report, planning,
Friends of the Earth , Greater London Council , public opinion,
flasks, mortality, Sellafield, Cap La Hague, emergency planning,
terrorism, nuclear power stations, planning applications
Held by the Research Library at the London Research Centre,
Parliament House, 81 Black Prince Road, London SE1 7SZ, UK.
Tel:071-627-9666 Fax:071-627-9674. Copies of articles are
available by post - please contact the address/phone above for
cost and a copyright declaration from. Books, pamphlets and other
items are available through the inter-library loan scheme.